Summary of construction timescales Phase of work Types of activity Approximate timetable Engaging with customers and stakeholders about the preferred route Sharing the route, listening to feedback February/March 2022 Environmental investigations Archaeological surveys and ecological monitoring Ongoing until autumn 2022 Ground investigations and archaeological trial pits Digging trenches and boreholes to understand conditions below the surface Ongoing until summer 2022 Submission of planning application and Environmental Impact Assessment Ongoing discussions with planning authorities Summer 2022 Enabling works (works needed prior to the start of construction) Providing ecological protection for protected species such as badgers Limited vegetation removal, including some hedgerows to aid access Winter 2023 Construction Site compounds set-up Cutting open trenches, laying pipes and backfilling (refilling of soil once the pipe has been installed) Trenchless pipelaying (when pipes are pushed through the ground) Construction of pumping stations at Elsham, Welton and Waddington, and water storage tank and conditioning plant at Elsham Temporary storage lagoons (to store water that is washed out of the pipeline during testing) Spring 2023 until 2024 Commissioning (testing of the pipeline prior to becoming operational) Cleaning the pipeline and connecting to network Late 2024 / early 2025 Reinstatement after installation (the land will be reinstated to its original state where we can and with additional improvements in some areas) Replacement of topsoil, restoration of access routes and reinstatement of road surfaces, drainage and vegetation Starting in 2023 and continuing until summer 2024